Sunday, May 17, 2015

CC6 Speech:PMP-Project Mismanagement Professionals



Good morning fellow toastmasters, first I would like to ask you the full form of PMP. Yes, that’s correct, it is Project management professionals.

But today my topic is about a different PMP which came to my mind-Project mismanagement professionals.  I have worked for few months in a construction site of a large project. On a daily basis, I have witnessed people dealing issues in an emotional way and not in an intellectual and structured way as mentioned in the original PMP. Kind and Gentleness ends up at the Project office. Once we are at the construction site, it is always chaos & fighting. I am going to enact what happens at site level with a small conversation.

This is a site progress meeting between the client and Vendor.

(Threatening, high voice)
Client:  “Where is your DPR-Daily progress report”? Vendor hands over it.
Client “What, as per yesterday’s commitment you have promised to pull 200 meter of cables from pillar A to pillar B but only 50% is completed. What is the reason?”
Vendor “Sir yesterday we are unable to do it. But we will do it today without fail”
Client “Did you not hear what I said, I asked why you did not do it yesterday”
Vendor “err…sir…We are unable to use the drilling machines as power was shut down by the electrical department “
Client “Is it my problem, it is your problem…as per contract it’s a turnkey project for you. So you have to arrange for power if power not available. This is not a logical reason; tell me why you have not done the work yesterday”
Vendor “Sir Safety team stopped the work since my guys are not wearing helmet, also interior team is not allowing us to touch the ceiling to do the work”
Client “Is it my problem it is your problem. As per contract you have to adhere to the safety procedures & dealing with interior team. It is your mistake. I don’t want to hear any more reasons; I want you to complete the works today in addition to the work lapsed yesterday”
Vendor” No sir it is very difficult. It is not possible to do it today we don’t have the required manpower”
Client “how dare you say that it cannot be done. If you are not doing today, I will put heavy fine for delaying the work”
Vendor in a frustrated tone says “Sir we cannot do that much work today. You do whatever you want, we cannot do it today”. He walks out of the meeting.

This is how a usual site progress meeting happens in almost in all construction projects. The above conversation is an example of Project mismanagement professional. There is always a master/slave relationship between client and vendor. The client comes to the meeting with his ears shut and in a threatening mood. Vendor comes with a bag of excuses, lot of delaying tactics and passes the buck to other departments. Both the client and vendor lose their temper and get disturbed emotionally and physically and end up in losing their health with BP & hypertension.  

So, Again we have the same conversation in a different manner.

(Soft tone)
Client “Where is your DPR”.Vendor hands over it.
Client “as per yesterday’s commitment you have promised to pull 200 meter of cables from pillar A to pillar B but only 50% is completed. What is the reason?”
Vendor “Sir, My apologies first and there are few reasons due to which we are unable to do the work”
Vendor “You apologies are fine. But I am disappointed that you have not escalated to me yesterday itself as my mobile can be reached 24/7.We have lost a day’s time. Now tell me the reason.”
Vendor “err…sir…We are unable to use the drilling machines as power was shut down by the electrical department “
Client “I will speak to electrical team and ensure power does not go off. But also arrange a standby power at your end if it goes out intermittently”
Vendor “Sir Safety team stopped the work since my guys are not wearing helmet”
Client    “Your vendors can take the safety helmet/jackets from our team. They will lend it for today”
Client “Forget about interior team, I am giving my approval to touch the ceiling. I will personally assure them no damage will happen.”
Vendor “We don’t have enough manpower today”
Client “You speak to your manager and push few people from other site as we cannot support on this. Please inform your manager to arrange as it is a very urgent work”
Vendor “Ok sir”.

If this kind of cohesive environment as per the above conversation exists, people will not have undue tension. The client and vendor should have a collaborative relationship. This will help them to achieve desired results.


I would like to conclude that for large projects, steps need to be taken to implements that PMP kind of standard must not stop with project office alone. It must properly transcend to the site where the real action takes place. If implemented, it will greatly improve the productivity and also the quality of the life of people working at the construction sites. So people can avoid being Project mismanagement professionals and become Good project management professionals.

0 comments:

Post a Comment